Lahore Airport Main Runway to be Reconstructed and Secondary Runway to be Upgraded
-
- Registered Member
- Posts: 1314
- Joined: Wed Jan 07, 2015 4:40 am
- Location: Hong Kong/VHHH
Re: Lahore Airport Main Runway to be Reconstructed and Secondary Runway to be Upgraded
Islamabad’s Runway is made of Asphalt.

Special Concept Livery to celebrate Pakistan's 70th year of Independence
-
- Registered Member
- Posts: 244
- Joined: Thu Apr 06, 2006 5:18 pm
- Location: LONDON (UK)
Re: Lahore Airport Main Runway to be Reconstructed and Secondary Runway to be Upgraded
I think it is concrete, please have a look at my photos of the runway.
KHURRAM JADOON - LONDON (UK)
-
- Registered Member
- Posts: 776
- Joined: Mon Dec 31, 2007 8:07 am
- Location: Dubai, UAE
Re: Lahore Airport Main Runway to be Reconstructed and Secondary Runway to be Upgraded
Both runways of Islamabad (10L 28R and 10R 28 L) are asphalt
-
- Registered Member
- Posts: 244
- Joined: Thu Apr 06, 2006 5:18 pm
- Location: LONDON (UK)
Re: Lahore Airport Main Runway to be Reconstructed and Secondary Runway to be Upgraded
We are discussing Lahore's new runway.
KHURRAM JADOON - LONDON (UK)
-
- Site Admin
- Posts: 54584
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Lahore Airport Main Runway to be Reconstructed and Secondary Runway to be Upgraded
From April 12 to May 31.
Heavy equipment/machinery deployed on 'Taxiway A' due to runway reconstruction work. Aircraft landing on Runway 36L and taking off from Runway 18R may exercise caution. Day and night marking/lights remain displayed on machinery/equipment for the safety of aircraft.

Lahore Airport taxiways can be seen in this chart:

Lahore Airport runways:
Main Runway 18L/36R
Secondary Runway 18R/36L

Abbas
Heavy equipment/machinery deployed on 'Taxiway A' due to runway reconstruction work. Aircraft landing on Runway 36L and taking off from Runway 18R may exercise caution. Day and night marking/lights remain displayed on machinery/equipment for the safety of aircraft.

Lahore Airport taxiways can be seen in this chart:

Lahore Airport runways:
Main Runway 18L/36R
Secondary Runway 18R/36L

Abbas
-
- Registered Member
- Posts: 351
- Joined: Sat Apr 18, 2015 11:33 am
- Location: Lahore
Re: Lahore Airport Main Runway to be Reconstructed and Secondary Runway to be Upgraded
Dear Abbas Bhai,
Lahore airport runway map has been updated on Google Maps.
Lahore airport runway map has been updated on Google Maps.
EK, EY, SV, PK, AIR BLUE, EASY JET, AA, TG, MH, FLY BE, VUELING, SAS, SWISS, LH, BA, AIR BERLIN, RYAN AIR, GERMAN WINGS, JET BLUE, U.A, QATAR , AZAL ...
-
- Site Admin
- Posts: 54584
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Lahore Airport Main Runway to be Reconstructed and Secondary Runway to be Upgraded
^ Thank you Omair for the info.
Lahore Airport runways:
Main Runway 18L/36R
Secondary Runway 18R/36L

Abbas
Lahore Airport runways:
Main Runway 18L/36R
Secondary Runway 18R/36L

Abbas
-
- Site Admin
- Posts: 54584
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Lahore Airport Main Runway to be Reconstructed and Secondary Runway to be Upgraded
Pakistan Civil Aviation Authority (CAA) has suspended a Senior Director/Project Director, Allama Iqbal International Air Port (AIIAP) - Lahore for displaying negligence and inefficiency in Lahore Airport Runway Reconstruction Project. He allowed grant of Extension of Time (EoT) to the contractor without the approval of the competent authority.

Abbas

Abbas
-
- Registered Member
- Posts: 1126
- Joined: Sat Jan 26, 2008 7:26 pm
- Location: Edinburgh
Re: Lahore Airport Main Runway to be Reconstructed and Secondary Runway to be Upgraded
Full Pay and allowances continue whilst breaking the rules, wah ji.
Also Shehbaz bhai ab to 5 days kay under ye runway bhi khula day
In all seriousness, has there been any deadline given to complete the runway. I really do hope the airport also upgrades the secondary runway too.
Also Shehbaz bhai ab to 5 days kay under ye runway bhi khula day


In all seriousness, has there been any deadline given to complete the runway. I really do hope the airport also upgrades the secondary runway too.
-
- Site Admin
- Posts: 54584
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Lahore Airport Main Runway to be Reconstructed and Secondary Runway to be Upgraded
From April 29 to May 10
Taxiway centerline lights, edge lights and guidance lights are not available on Taxiway P and part of Taxiway N and part of apron due to ongoing runway reconstruction work.

Lahore Airport taxiways can be seen in this chart:

Abbas
Taxiway centerline lights, edge lights and guidance lights are not available on Taxiway P and part of Taxiway N and part of apron due to ongoing runway reconstruction work.

Lahore Airport taxiways can be seen in this chart:

Abbas
-
- Site Admin
- Posts: 54584
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Lahore Airport Main Runway to be Reconstructed and Secondary Runway to be Upgraded
From May 9 to May 16
Taxiway centerline lights, edge lights and guidance sign lights are not available on Taxiway P and part of Taxiway N and part of apron due to ongoing runway reconstruction work.

Lahore Airport taxiways can be seen in this chart:

Abbas
Taxiway centerline lights, edge lights and guidance sign lights are not available on Taxiway P and part of Taxiway N and part of apron due to ongoing runway reconstruction work.

Lahore Airport taxiways can be seen in this chart:

Abbas
-
- Site Admin
- Posts: 54584
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Lahore Airport Main Runway to be Reconstructed and Secondary Runway to be Upgraded
From May 16 to May 30
Taxiway centerline lights, edge lights and guidance sign lights are not available on Taxiway P and part of Taxiway N and part of apron due to ongoing runway reconstruction work.

Lahore Airport taxiways can be seen in this chart:

Abbas
Taxiway centerline lights, edge lights and guidance sign lights are not available on Taxiway P and part of Taxiway N and part of apron due to ongoing runway reconstruction work.

Lahore Airport taxiways can be seen in this chart:

Abbas
-
- Site Admin
- Posts: 54584
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Lahore Airport Main Runway to be Reconstructed and Secondary Runway to be Upgraded
From June 1, 2022, to June 30, 2022
Taxiway Alpha closed for flight operations. Heavy machinery in operation. Pilots are to exercise extreme caution while using Runway 18R/36L.

Lahore Airport taxiways can be seen in this chart:

Lahore Airport runways:
Main Runway 18L/36R
Secondary Runway 18R/36L

Abbas
Taxiway Alpha closed for flight operations. Heavy machinery in operation. Pilots are to exercise extreme caution while using Runway 18R/36L.

Lahore Airport taxiways can be seen in this chart:

Lahore Airport runways:
Main Runway 18L/36R
Secondary Runway 18R/36L

Abbas
-
- Registered Member
- Posts: 2087
- Joined: Sat Jul 15, 2006 4:52 am
Re: Lahore Airport Main Runway to be Reconstructed and Secondary Runway to be Upgraded
Yes there may be other factors involved, yet amazing that northern rwy (30R/12L) reconstruction at DXB, which involved similar work as being done at lahore, has been completed in exactly 45 days, while at lahore it has taken almost 2 years and still not complete. Started on 9 May, planned opening 22 Jun.Abbas Ali wrote: Wed Jun 01, 2022 9:57 pm From June 1, 2022, to June 30, 2022
Taxiway Alpha closed for flight operations. Heavy machinery in operation. Pilots are to exercise extreme caution while using Runway 18R/36L.
............................
Abbas
-
- Site Admin
- Posts: 54584
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Lahore Airport Main Runway to be Reconstructed and Secondary Runway to be Upgraded
Reconstructed Main Runway 18L/36R of Lahore Airport expected to become available for flight operations after Eid al-Adha. A ceremony is being planned for the re-opening of runway.
* Runway 18L/36R civil works completed in April 2022.
* Runway 18L/36R electrification works completed in June 2022.
Lahore Airport runways:
Main Runway 18L/36R
Secondary Runway 18R/36L

Abbas
* Runway 18L/36R civil works completed in April 2022.
* Runway 18L/36R electrification works completed in June 2022.
Lahore Airport runways:
Main Runway 18L/36R
Secondary Runway 18R/36L

Abbas