New Gwadar International Airport Project
-
- Site Admin
- Posts: 53449
- Joined: Thu Aug 05, 2004 11:52 pm
- Location: Pakistan
Re: New Gwadar International Airport Project
National Engineering Services Pakistan (NESPAK) has invited bids from drilling contractors/companies for carrying out geotechnical investigations for new Gwadar International Airport project.
Bids invitation in February 4 newspaper:
Abbas
Bids invitation in February 4 newspaper:
Abbas
-
- Site Admin
- Posts: 53449
- Joined: Thu Aug 05, 2004 11:52 pm
- Location: Pakistan
Re: New Gwadar International Airport Project
Pakistan Civil Aviation Authority (CAA) bids invitation in March 4 newspaper:
Package-I
* Power Supply System along fence.
* Security monitoring & control system
* Watch towers (liveable and non-liveable)
* Office cum accommodation of company commander (COY), Sector Commander (SC), Staff, Communication Room, Quick Response Force (QRF), sheds etc.
Corrigendum in March 6 newspaperman clarifying that March 4 advertisement is for location new Gwadar International Airport.
Abbas
Package-I
* Power Supply System along fence.
* Security monitoring & control system
* Watch towers (liveable and non-liveable)
* Office cum accommodation of company commander (COY), Sector Commander (SC), Staff, Communication Room, Quick Response Force (QRF), sheds etc.
Corrigendum in March 6 newspaperman clarifying that March 4 advertisement is for location new Gwadar International Airport.
Abbas
-
- Site Admin
- Posts: 53449
- Joined: Thu Aug 05, 2004 11:52 pm
- Location: Pakistan
Re: New Gwadar International Airport Project
Pakistan Civil Aviation Authority (CAA) invitation for bids in May 2 newspaper:
New Gwadar International Airport Project
Package-II
Construction of CAA Residential Complex, Cargo Building and External Services from Pakistan CAA's own resources and Public Sector Development Programme (PSDP) fund.
Broadly the works include but are not limited to the following:
* Building Works
* Road Networks
* Infrastructure Works (Water Supply, Power Supply, Telecommunication etc. External & Internal)
* Sewerage Treatment Plant
Abbas
New Gwadar International Airport Project
Package-II
Construction of CAA Residential Complex, Cargo Building and External Services from Pakistan CAA's own resources and Public Sector Development Programme (PSDP) fund.
Broadly the works include but are not limited to the following:
* Building Works
* Road Networks
* Infrastructure Works (Water Supply, Power Supply, Telecommunication etc. External & Internal)
* Sewerage Treatment Plant
Abbas
-
- Site Admin
- Posts: 53449
- Joined: Thu Aug 05, 2004 11:52 pm
- Location: Pakistan
Re: New Gwadar International Airport Project
The greenfield Gwadar International Airport being built over an area of 4,300 acres would be made operational by September 2023.
* Work related to air traffic control would be completed by March 2023.
* Passenger terminal building of the project would be completed by June 2023.
* Overall construction of the airport would be finished before September 2023.
The new Gwadar International Airport will be managed and operated by Civil Aviation Authority (CAA). The airport is a joint venture between Pakistan, Oman, and China, the airport would handle domestic and international operations. The airport development is a part of China-Pakistan Economic Corridor (CPEC) development, which was a cornerstone of China’s One Belt One Road (OBOR) initiative.
The airport would be capable of handling Airbus A380 aircraft upon its commissioning. It will stimulate the development in Gwadar peninsula and boost trade between Pakistan and China. The airport would be operated under open skies policy and developed under the guidance of the Civil Aviation Authority (CAA).
The new Gwadar International Airport project was initiated as an early harvest high-priority project of the CPEC programme in 2014.
It was approved by the Executive Committee of National Economic Council (ECNEC) in January 2015. The project is being funded through a grant agreement signed between China and Pakistan in May 2017. Soil testing on the project site was started in January 2018 and involved drilling of 300 boreholes in various locations. The groundbreaking ceremony was held in March 2019.
Source: APP
* Work related to air traffic control would be completed by March 2023.
* Passenger terminal building of the project would be completed by June 2023.
* Overall construction of the airport would be finished before September 2023.
The new Gwadar International Airport will be managed and operated by Civil Aviation Authority (CAA). The airport is a joint venture between Pakistan, Oman, and China, the airport would handle domestic and international operations. The airport development is a part of China-Pakistan Economic Corridor (CPEC) development, which was a cornerstone of China’s One Belt One Road (OBOR) initiative.
The airport would be capable of handling Airbus A380 aircraft upon its commissioning. It will stimulate the development in Gwadar peninsula and boost trade between Pakistan and China. The airport would be operated under open skies policy and developed under the guidance of the Civil Aviation Authority (CAA).
The new Gwadar International Airport project was initiated as an early harvest high-priority project of the CPEC programme in 2014.
It was approved by the Executive Committee of National Economic Council (ECNEC) in January 2015. The project is being funded through a grant agreement signed between China and Pakistan in May 2017. Soil testing on the project site was started in January 2018 and involved drilling of 300 boreholes in various locations. The groundbreaking ceremony was held in March 2019.
Source: APP
-
- Site Admin
- Posts: 53449
- Joined: Thu Aug 05, 2004 11:52 pm
- Location: Pakistan
Re: New Gwadar International Airport Project
First test flight to be conducted at new Gwadar International Airport by the end of December 2022.
The greenfield airport built over an area of 4,300 acres is expected to become fully operational by the end of September 2023.
Abbas
The greenfield airport built over an area of 4,300 acres is expected to become fully operational by the end of September 2023.
Abbas
-
- Site Admin
- Posts: 53449
- Joined: Thu Aug 05, 2004 11:52 pm
- Location: Pakistan
Re: New Gwadar International Airport Project
New Gwadar International Airport to be inaugurated on March 23, 2023, and flight operations will be shifted from current Gwadar Airport to the new airport.
Abbas
Abbas
-
- Site Admin
- Posts: 53449
- Joined: Thu Aug 05, 2004 11:52 pm
- Location: Pakistan
Re: New Gwadar International Airport Project
Today, Prime Minister Shehbaz Sharif directed authorities to ensure completion of new Gwadar International Airport construction work by the end of July 2023.
Maybe inauguration of new Gwadar International Airport to take place on Pakistan Independence Day anniversary on August 14, 2023.
Abbas
-
- Site Admin
- Posts: 53449
- Joined: Thu Aug 05, 2004 11:52 pm
- Location: Pakistan
Re: New Gwadar International Airport Project
New Gwadar International Airport Project
Package-III Construction of Airports Security Force (ASF) Camp
Pakistan Civil Aviation Authority (CAA) invites sealed bids for construction of Airports Security Force (ASF) Camp at new Gwadar International Airport.
Construction of Airports Security Force (ASF) Camp at new Gwadar International Airport has been funded by Pakistan CAA's own resources and Public Sector Development Programme (PSDP) fund.
Broadly the works include but are not limited to the following:
Building works
Roads network
Infrastructure works (water supply, storm water drainage, fire fighting, power supply, telecommunication works etc.)
In July 2 newspaper:
Abbas
Package-III Construction of Airports Security Force (ASF) Camp
Pakistan Civil Aviation Authority (CAA) invites sealed bids for construction of Airports Security Force (ASF) Camp at new Gwadar International Airport.
Construction of Airports Security Force (ASF) Camp at new Gwadar International Airport has been funded by Pakistan CAA's own resources and Public Sector Development Programme (PSDP) fund.
Broadly the works include but are not limited to the following:
Building works
Roads network
Infrastructure works (water supply, storm water drainage, fire fighting, power supply, telecommunication works etc.)
In July 2 newspaper:
Abbas
-
- Site Admin
- Posts: 53449
- Joined: Thu Aug 05, 2004 11:52 pm
- Location: Pakistan
Re: New Gwadar International Airport Project
Artist's impression of new Gwadar International Airport
New Gwadar International Airport built on an area of 4,300 acres expected to become operational by September 2023.
The new airport is being managed and operated by Pakistan Civil Aviation Authority (CAA) and is owned by a tripartite venture between Pakistan, Oman, and China.
The under construction passenger terminal building of new Gwadar International Airport
It's part of China Pakistan Economic Corridor (CPEC) of China’s One Belt One Road (OBOR) initiative.
The new airport will play important role in the development of Gwadar hammer head peninsula and enhance trade ties between Pakistan and China.
Terminal building of the existing Gwadar International Airport
Abbas
-
- Site Admin
- Posts: 53449
- Joined: Thu Aug 05, 2004 11:52 pm
- Location: Pakistan
Re: New Gwadar International Airport Project
National Engineering Services Pakistan (NESPAK) - http://nespak.com.pk/ - has won Project Management Consultancy (PMC) services in an open bidding for new Gwadar International Airport construction project.
Abbas
-
- Site Admin
- Posts: 53449
- Joined: Thu Aug 05, 2004 11:52 pm
- Location: Pakistan
Re: New Gwadar International Airport Project
China's Hytera will install modern communications system and equipment at new Gwadar International Airport including:
DIB-R5 Compact Tetra Base Station
SmartOne Dispatch
Multiple portable radios
Mobile radios
Repeaters
Abbas
DIB-R5 Compact Tetra Base Station
SmartOne Dispatch
Multiple portable radios
Mobile radios
Repeaters
Abbas
-
- Site Admin
- Posts: 53449
- Joined: Thu Aug 05, 2004 11:52 pm
- Location: Pakistan
Re: New Gwadar International Airport Project
Under construction terminal building of new Gwadar International Airport.
Artist's impression of new Gwadar International Airport terminal building.
New Gwadar International Airport expected to become operational by the end of year 2023.
Abbas
-
- Registered Member
- Posts: 3019
- Joined: Fri Aug 06, 2004 12:10 am
- Location: Lahore
Re: New Gwadar International Airport Project
very nice.
The ATR42-500 flying to Gwader will have the entire airport to itself.
The ATR42-500 flying to Gwader will have the entire airport to itself.
P.I.A
God's International Airline
God's International Airline
-
- Registered Member
- Posts: 73
- Joined: Sun Jun 26, 2022 9:24 pm
Re: New Gwadar International Airport Project
Gwadar Airport's traffic load should increase as a logical consequence of the port's development. A much simpler and functional airport would've been a better choice though.Amaad Lone wrote: ↑Sat Sep 03, 2022 11:48 pm very nice.
The ATR42-500 flying to Gwader will have the entire airport to itself.
Make the 100% correct decision 100% of the time.
-
- Site Admin
- Posts: 53449
- Joined: Thu Aug 05, 2004 11:52 pm
- Location: Pakistan
Re: New Gwadar International Airport Project
Today, Aviation Minister Khawaja Saad Rafique at a press briefing held at Lahore Airport informed:
Opening of new Gwadar International Airport expected in March 2023.
Completion of new Gwadar International Airport projected expected by mid-2023.
Abbas