Lahore Airport Runways, Taxiways and Apron Maintenance Work

Discuss issues and news related to PIA, Pakistani airlines and Pakistan's civil & military aviation.
User avatar
Abbas Ali
Site Admin
Posts: 54798
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Lahore Airport Runways, Taxiways and Apron Maintenance Work

Post by Abbas Ali »

From July 16 to September 30, Taxiway J will not be available due to rehabilitation work on Taxiway H. Heavy machinery and laborers will be deployed.

All pilots advised to exercise caution while taxi in/out to/from PAF tarmac.

Image

From July 17 to October 16, Taxiway H will remain closed for rehabilitation work.

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 54798
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Lahore Airport Runways, Taxiways and Apron Maintenance Work

Post by Abbas Ali »

From July 24, Runway 36L/18R is available for flight operations having following characteristics

LENGTH AND WIDTH: 2743 X 46M
SHOULDERS: NOT PROVIDED
PCN: 69/F/C/X/U
THRESHOLD COORDINATES:
36L (313033.099N 742408.60E)
18R (313202.104N 742410.188E)
STOPWAY: 36L(274M) AND 18R(244M)
CLEARWAY: 36L(274M) AND 18R(244M) RESA 36L (92 X 90M)
SECONDARY RUNWAY: 36L PRECISION APPROACH CAT-1 WITH SIMPLE APPROACH LIGHTING SYSTEM

AIRLINES TO OPERATE AIRCRAFT COMPATIBLES WITH PCN VALUE 69/F/C/X/U OF SECONDARY RUNWAY 36L/18R

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 54798
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Lahore Airport Runways, Taxiways and Apron Maintenance Work

Post by Abbas Ali »

From August 6 to September 30, bay numbers 29 and 30 will not be available for parking aircraft due to rehabilitation work.

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 54798
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Lahore Airport Runways, Taxiways and Apron Maintenance Work

Post by Abbas Ali »

From September 30 to November 30

Bay numbers 29 and 30 will not be available for parking aircraft due to rehabilitation work.

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 54798
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Lahore Airport Runways, Taxiways and Apron Maintenance Work

Post by Abbas Ali »

From October 15 to December 31.

Lahore Airport secondary Runway 18R/36L will be closed for one to two hours on selected days (Monday. Wednesday, Thursday & Friday) for maintenance. In case of operational requirements, the runway will be made available under a ten-minute advance notice.

15TH OCT TO 31ST DEC'2020
MON BTN 0955-1130
WED BTN 0930-1130
THU BTN 1000-1130
FRI BTN 1030-1130

Image

The airport's main Runway 18L/36R is closed for reconstruction.

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 54798
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Lahore Airport Runways, Taxiways and Apron Maintenance Work

Post by Abbas Ali »

From October 21, 2020, to March 31, 2021

Taxiway 'H' (Hotel) shall remain closed for rehabilitation work. Area under rehabilitation starts from 500 feet west of Taxiway 'K' and 'H'. Heavy machinery is placed in the area. Taxi in procedure from secondary runway shall be follow 'H'' taxiway track till its junction with taxiway 'K''. Follow taxiway 'K' taxi track to enter Pakistan Air Force (PAF) tarmac. Taxi out procedure from PAF tarmac shall be follow taxiway 'K' taxi link till its junction with taxiway 'H' Taxi track (N) M turn left to onto taxiway 'H' till intermediate holding position of taxiway 'K'. Pilots are exercise to extreme caution as heavy machine and personnel are working in the area and Foreign Object Debris (FOD) presence is also to be avoided.

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 54798
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Lahore Airport Runways, Taxiways and Apron Maintenance Work

Post by Abbas Ali »

From November 6.

Isolated parking bay has been relocated from Taxiway S to aircraft parking bay number 22.

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 54798
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Lahore Airport Runways, Taxiways and Apron Maintenance Work

Post by Abbas Ali »

From January 1 to March 31

Lahore Airport secondary Runway 18R/36L shall remain closed for maintenance work. However, in case of any operational requirements, it shall be made operational within ten minutes notice.

Monday from 0955 to 1130 (one hour & thirty-five minutes)
Wednesday from 0930 to 1130 (two hours)
Thursday from 1000 to 1130 (one hour & thirty minutes)
Friday from 1030 to 1130 (one hour)

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 54798
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Lahore Airport Runways, Taxiways and Apron Maintenance Work

Post by Abbas Ali »

From March 26 to September 30, Lahore Airport Taxiway H will remain closed for rehabilitation work.

Pilots advised to exercise extreme caution as heavy machinery and personnel will be working in the area. Foreign Object Debris (FOD) also to be avoided.

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 54798
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Lahore Airport Runways, Taxiways and Apron Maintenance Work

Post by Abbas Ali »

From July 1 to December 31

Lahore Airport secondary Runway 18R/36L shall remain closed for maintenance.

Runway 18R/36L maintenance work schedule:

Monday 9:55 AM to 11:30 AM
Wednesday 9:30 AM to 11: 30 AM
Thursday 10:00 AM to 11:30 AM
Friday 10:30 AM to 11:30 AM

However, in case of operational requirement Runway 18R/36L will be made available within ten-minute prior notice.

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 54798
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Lahore Airport Runways, Taxiways and Apron Maintenance Work

Post by Abbas Ali »

From January 1, 2022, to February 21, 2022.

Lahore Airport secondary Runway 18R/36L shall remain closed due to maintenance work as per details given below. However, in case of any operational requirements Runway 18R/36L will be made available within 10 minutes prior notice.

Monday 0955-1130 (1 hour & 35 minutes)
Wednesday 0930-1130 (2 hours)
Thursday 1000-1130 (1 hour & 30 minutes)
Friday 1030-1130 (1 hour)

Image

Main Runway 18L/36R (being reconstructed)
Secondary Runway 18R/36L

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 54798
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Lahore Airport Runways, Taxiways and Apron Maintenance Work

Post by Abbas Ali »

From February 21 to April 15

Lahore Airport secondary Runway 18R/36L shall remain closed due to maintenance work as per given details. However, in case of any operational requirements, Runway 18R/36L will be made available within 10 minutes prior notice.

Monday 9:55 AM to 11:30 AM
Wednesday 9:30 AM to 11:30 AM
Thursday 10:00 AM to 11:30 AM
Friday 10:30 AM to 11:30 AM

Image

Lahore Airport runways:

Main Runway 18L/36R (being reconstructed)
Secondary Runway 18R/36L

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 54798
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Lahore Airport Runways, Taxiways and Apron Maintenance Work

Post by Abbas Ali »

From April 12 to May 31

Lahore Airport secondary Runway 18R/36L shall remain closed due to maintenance work as per given details. However, in case of any operational requirements, Runway 18R/36L will be made available within 10 minutes prior notice.

Monday 0955-1130
Wednesday 0930-1130
Thursday 1000-1130
Friday 1030-1130

Image

Lahore Airport runways:

Main Runway 18L/36R (being reconstructed)
Secondary Runway 18R/36L

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 54798
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Lahore Airport Runways, Taxiways and Apron Maintenance Work

Post by Abbas Ali »

From April 21, Lahore Airport Taxiway H is fully rehabilitated and operational except installation of taxiway edge lights. Taxiway H is available in daylight hours only.

Image

Lahore Airport taxiways can be seen in this chart:

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 54798
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Lahore Airport Runways, Taxiways and Apron Maintenance Work

Post by Abbas Ali »

Notice to Airmen (NOTAM) issued:

From November 11, 2022.

Lahore Airport Taxiway H (Hotel taxi track) is operational.

Taxiway H information:

Rehabilitated portion of Taxiway H

Rehabilitated portion of Taxiway H after normal portion dimensions:

Length 1758 feet
Width 75.5 feet
PCN 49/F/C/X/T

Normal portion of Taxiway H

Normal portion of Taxiway H from the edge of Runway 18R/36L dimensions:

Length 810 feet
Width 75.5 feet
PCN 10/F/D/Y/T

A. Taxiway edge lights available
B. Day and night operation is available for compatible aircraft
C. Taxiway edge markings available

Image

Lahore Airport taxiways can be seen in this chart:

Image

Abbas