From August 27 to September 30, rehabilitation work in progress on western side of runway approximately 1500 feet down the Runway 21 and 315 feet from runway centre line. Heavy machinery have been deployed. All pilots advised to exercise caution while landing/takeoff/taxiing.
From August 27 to September 30, in order to rehabilitate abandoned/secondary runway at Faisalabad International Airport, digging/refilling work has been completed while slab and asphalt laying work is in progress. Heavy machinery is deployed for the purpose. All pilots to exercise caution during landing/takeoff from Runway 03/21.
Asphalt laying work is in progress to rehabilitate abandoned secondary runway at Faisalabad International Airport. Heavy machinery can be seen deployed for the purpose.
Most likely secondary runway will become operational as Runway 03L/21R.
After secondary runway becomes operational, the primary Runway 03/21 will be upgraded to handle Boeing 777 category aircraft. Most likely, the upgraded primary runway will become Runway 03R/21L.
From September 30 to October 31, in order to rehabilitate abandoned/secondary runway at Faisalabad International Airport, digging/refilling work has been completed while slab and asphalt laying work is in progress. Heavy machinery is deployed for the purpose. All pilots advised to exercise caution during landing/takeoff from Runway 03/21.
Pakistan Civil Aviation Authority (CAA) tender notice in November 29 newspaper for the construction of a new Fire Station and Allied Facilities at Faisalabad International Airport.
Faisalabad International Airport old Fire Station visible on right side of this photo.
in order to rehabilitate abandoned/secondary runway at Faisalabad International Airport, heavy machinery is deployed for the rehabilitation purpose. All pilots advised to exercise caution during landing/takeoff from Runway 03/21.
Pakistan Civil Aviation Authority (CAA) tender notice in December 31 newspaper for installation of new Doppler VHF Omni Directional Range (DVOR)/Distance Measuring Equipment (DME) at Faisalabad Airport.
Digging work in progress along right side of the Runway 03R approximately 260 feet from Runway 03R center line. Heavy machinery will be deployed for digging of area. All aircraft advised to exercise caution during landing and takeoff.
From January 5 to January 10.
Aircraft parking bay number 1 and 2 will be unavailable due to maintenance work on terminal building roof.
Opening of Pakistan Civil Aviation Authority (CAA) tender notice for installation of new Doppler VHF Omni Directional Range (DVOR)/Distance Measuring Equipment (DME) at Faisalabad Airport has been postponed, according to following corrigendum in January 21 newspaper.
From February 12, 2021, to August 12, 2022, Faisalabad Airport main Runway 03R/21L will remain closed for flight operations due to reconstruction work.
Aircraft operations at Faisalabad Airport will continue from airport's secondary Runway 03L/21R.
From February 26, 2021, to August 12, 2021, Faisalabad Airport main Runway 03R/21L will remain closed for flight operations due to reconstruction work.
Aircraft operations at Faisalabad Airport will continue from airport's secondary Runway 03L/21R.
Machinery will be deployed on main Runway 03R/21L. Pilots advised to exercise caution while landing/takeoff from secondary Runway 03L/21R0.
Faisalabad Airport main Runway 03R/21L reconstruction work completion expected by August 2022 at a cost PKR 3.58 billion.
The main runway will be equipped with modern Instrument Landing System (ILS) allowing flight operations in poor visibility.
The reconstructed main runway will be capable of handling Boeing 777 category wide-body passenger aircraft.
The reconstructed main runway will also open the airport to new international routes and foreign airlines.
The reconstructed main runway will also allow operation of wide-body cargo aircraft flights at the airport. It will help exporters from Faisalabad and adjacent areas in exporting their products to various countries around the world directly.