Lahore Airport Expansion Project
-
- Registered Member
- Posts: 82
- Joined: Wed Nov 02, 2022 4:29 pm
Re: Lahore Airport Expansion Project
Does that white rectangle marked as “expansion area” also include the grass land, because in updated google maps, the grass is gone and the land has been dug. So according to google maps, the expansion is much bigger than the one marked on the figure above.
-
- Site Admin
- Posts: 53904
- Joined: Thu Aug 05, 2004 11:52 pm
- Location: Pakistan
Re: Lahore Airport Expansion Project
Work on Lahore Airport passenger terminal building expansion project has been suspended due to flaw in building expansion design plan, according to news reports.
Revised design/plan to be prepared for passenger terminal building expansion.
Abbas
Revised design/plan to be prepared for passenger terminal building expansion.
Abbas
-
- Registered Member
- Posts: 189
- Joined: Thu Oct 27, 2022 7:08 pm
Re: Lahore Airport Expansion Project
Means we won't see expanded terminal until 2030 at least. IMO, PCAA should simply design a larger greenfield airport across Ravi near Shiekhupura connected to freeway to serve Lahore, Okara, Faisalabad and Sargodha regions. Expanding current airport will not serve anyone beyond Lahore...... it can only be an alternate for Amritsar at most.Abbas Ali wrote: Mon Aug 12, 2024 10:25 pm Work on Lahore Airport passenger terminal building expansion project has been suspended due to flaw in building expansion design plan, according to news reports.
Revised design/plan to be prepared for passenger terminal building expansion.
Abbas
-
- Site Admin
- Posts: 53904
- Joined: Thu Aug 05, 2004 11:52 pm
- Location: Pakistan
Re: Lahore Airport Expansion Project
Urdu daily "Dunya" (August 13, 2024, edition)
Delay in release of funds to construction company/contractor also mentioned as a reason behind suspension of Lahore Airport passenger terminal building expansion project work.
Abbas
-
- Registered Member
- Posts: 3057
- Joined: Fri Aug 06, 2004 12:10 am
- Location: Lahore
Re: Lahore Airport Expansion Project
Where will PCAA find 2 billion dollars to build a brand new airport that will be 70 kilometers from Lahore??Means we won't see expanded terminal until 2030 at least. IMO, PCAA should simply design a larger greenfield airport across Ravi near Shiekhupura connected to freeway to serve Lahore, Okara, Faisalabad and Sargodha regions. Expanding current airport will not serve anyone beyond Lahore...... it can only be an alternate for Amritsar at most.
This airport is connected to other parts of North Punjab through the motorway via ring road.
P.I.A
God's International Airline
God's International Airline
-
- Site Admin
- Posts: 53904
- Joined: Thu Aug 05, 2004 11:52 pm
- Location: Pakistan
Re: Lahore Airport Expansion Project
From October 16, 2024, to October 4, 2025.
Stand number 9 not available due to construction regarding expansion of terminal building towards southern side. Stand numbers 10 & 11 can be utilized by Airport Manager (if deemed appropriate from operations/safety aspects) for any emergency and while considering ongoing construction activities of project at site. Caution of heavy construction machinery deployed at concerned site, whereas all other stands and related facilities shall remain available.
Notice to Airmen (NOTAM) issued:
Aircraft parking stand numbers 9, 10 and 11 location at Lahore Airport.
Satellite view of the area.
Abbas
Stand number 9 not available due to construction regarding expansion of terminal building towards southern side. Stand numbers 10 & 11 can be utilized by Airport Manager (if deemed appropriate from operations/safety aspects) for any emergency and while considering ongoing construction activities of project at site. Caution of heavy construction machinery deployed at concerned site, whereas all other stands and related facilities shall remain available.
Notice to Airmen (NOTAM) issued:
Aircraft parking stand numbers 9, 10 and 11 location at Lahore Airport.
Satellite view of the area.
Abbas
-
- Site Admin
- Posts: 53904
- Joined: Thu Aug 05, 2004 11:52 pm
- Location: Pakistan
Re: Lahore Airport Expansion Project
In Lahore airport terminal building expansion project, the terminal building area currently used for domestic flights will become part of the area for international flights.
Information appears in this October 17 Pakistan Airports Authority (PAA) tender notice:
Abbas
Information appears in this October 17 Pakistan Airports Authority (PAA) tender notice:
Abbas
-
- Registered Member
- Posts: 3057
- Joined: Fri Aug 06, 2004 12:10 am
- Location: Lahore
Re: Lahore Airport Expansion Project
The old Lahore airport should have been re-built and domestic flights should have moved there and this airport should have only handled international flights.
If you were going to transit then a bus service between the the two airports.
If you were going to transit then a bus service between the the two airports.
P.I.A
God's International Airline
God's International Airline
-
- Registered Member
- Posts: 612
- Joined: Mon Dec 19, 2022 12:17 pm
Re: Lahore Airport Expansion Project
Lahore gets domestic flights only from one city: Karachi. Not sure if there's a need to relocate domestic operations just for one specific route. Lahore certainly isn't as busy as Karachi domestically.Amaad Lone wrote: Fri Oct 18, 2024 12:46 pm The old Lahore airport should have been re-built and domestic flights should have moved there and this airport should have only handled international flights.
If you were going to transit then a bus service between the the two airports.
-
- Site Admin
- Posts: 53904
- Joined: Thu Aug 05, 2004 11:52 pm
- Location: Pakistan
Re: Lahore Airport Expansion Project
Recent satellite image of passenger terminal building expansion project area at Allama Iqbal International Airport in Lahore.
PIA Technical Ground Support (TGS) shed to be shifted to new location at Lahore Airport due to airport's passenger terminal building expansion project.
Tender notice in October 20 newspaper:
Location of PIA TGS area including shed can be seen in following image:
Abbas
-
- Site Admin
- Posts: 53904
- Joined: Thu Aug 05, 2004 11:52 pm
- Location: Pakistan
Re: Lahore Airport Expansion Project
Lahore Airport passenger terminal building expansion plan. Apparently, number of passenger boarding bridges to be increased to 9 from 7 currently offered by the passenger terminal building.
Abbas
-
- Registered Member
- Posts: 82
- Joined: Wed Nov 02, 2022 4:29 pm
Re: Lahore Airport Expansion Project
WOWWWW What an “expansion” !!!
-
- Registered Member
- Posts: 3057
- Joined: Fri Aug 06, 2004 12:10 am
- Location: Lahore
Re: Lahore Airport Expansion Project
All decent countries have their airports shut from midnight to 6 am.
why is Lahore airport open 24 hours??
Shut all flights for 6 hours.
why is Lahore airport open 24 hours??
Shut all flights for 6 hours.
P.I.A
God's International Airline
God's International Airline
-
- Registered Member
- Posts: 465
- Joined: Tue Dec 07, 2010 2:52 pm
- Location: Trento, Italy
Re: Lahore Airport Expansion Project
Because those “important” airlines like EK, EY, TY, QR, SV take the passengers in these hours to/from Pakistan due to their flight connections. We are such unfortunate nation that our national carrier can’t go to those western destinations where most of expats live.Amaad Lone wrote: Wed Dec 18, 2024 1:56 pm All decent countries have their airports shut from midnight to 6 am.
why is Lahore airport open 24 hours??
Shut all flights for 6 hours.
-
- Registered Member
- Posts: 612
- Joined: Mon Dec 19, 2022 12:17 pm
Re: Lahore Airport Expansion Project
Mismanagement at Pakistani airports is a bigger issue than the amount of space available.