thank you VirtualPia, lol...SIAL has alternative source of power in case of power failure from WAPDA
vpiahr, work is in progress and hope to share some more screenshots soon....3d lights for runway 22 also completed. currently working on the taxiway / appron and then markings of the same. Once, taxiway/appron details are finished then will be finalizing the AFCAD file as per the ground texturing. After that will be coming to the 3d building structures.
3d lights - appron, runway 04 & 22 and taxiway are completed
3d signs are completed
PSO station - almost completed; just needed to put some GSEs of PSO
ATC building in progress
Next will be...
Fire service block
Temp terminal block
Main terminal block
Just to inform that main terminal work is in progress along with security fencing and hopefully it will be completed this week, screenshots will be released soon.
some of the remaining work will be:
road ways, parking, water tank tower, complete lights (the main core issue of this project) and some small administrative blocks etc.
Here are some screenshots of the latest update, some details of the main terminal are fictious as not enough pictures available on the net. AFCAD needed to be refixed due to some resizing.