Due to reconstruction work of Faisalabad Airport main Runway 03R/21L, concrete batch plant (silo) is installed at 312136.108n 725935.635e at a distance of 292.37m and hut at 312138.6244n 725935.531e at a distance of 186.308m on eastern side from centre line of secondary Runway 03L/21R.
Pilots advised to exercise caution during landing/takeoff from secondary Runway 03L/21R.
Completion of Faisalabad Airport main Runway 03R/21L reconstruction work expected by August 2022.
The reconstructed and upgraded main runway will enable operation of Boeing 777 category passenger and cargo aircraft at the airport. It will increase passenger and cargo traffic at the airport.
Digging work in progress on eastern side of Runway 03L/21R approximately 1500 feet down Runway 21R and 75 feet from centre line. Heavy machinery has been deployed. All pilots advised to exercise caution while landing/takeoff/taxiing.
From April 18 to May 31
Digging work in progress on eastern side of secondary Runway 03L/21R approximately 2500 feet down Runway 03L abeam Taxiway B and 75 feet from center line. Heavy machinery have been deployed. All pilots advised to exercise caution while landing/takeoff/taxiing.
Today, Aviation Minister Khawaja Saad Rafique chaired a meeting at Faisalabad International Airport where he received briefing on airport's main runway reconstruction project.
Faisalabad Airport primary Runway 03R/21L being upgraded for regular Boeing 777 category passenger and cargo aircraft operations is expected to become operational in October this year. Flights between Faisalabad and UK (Manchester and Glasgow) to be considered after completion of runway upgrade work.
Proposals to be submitted for Faisalabad International Airport Cargo Terminal construction and passenger lounge upgradation.
70% work has been completed to upgrade Faisalabad Airport primary Runway 03R/21L. The upgraded runway is expected to become operational by the end of October this year.
The upgraded runway will be capable of handling regular Boeing 777 category passenger and cargo aircraft operations at Faisalabad Airport.
Faisalabad Airport runways:
Primary Runway 03R/21L
Secondary Runway 03L/21R
Completion of 75% work on under construction Cargo Complex also expected by the end of October this year.
Digging work for construction of water drainage channel (5 feet wide and 5 feet deep) on eastern side of Secondary Runway 03L/21R and 137 feet all along from centre line is in progress. Heavy machinery has been deployed. All pilots advised to exercise caution while landing/takeoff/taxiing.
Digging work in progress on eastern side of secondary Runway 03L/21R approximately 2,500 feet down the Runway 03L abeam Taxiway B and 75 feet from center line. Heavy machinery has been deployed. All pilots advised to exercise caution while landing/takeoff/taxi.
Pakistan Civil Aviation Authority (CAA) tender notice in September 17 newspaper for rehabilitation of existing localizer antenna foundation and localizer hut at main runway of Faisalabad Airport.
Digging work in progress on both sides approximately 3400 feet down the Runway 03L (02 feet wide and 03 feet deep) and 75 feet from centre line. All pilots advised to exercise caution while landing/takeoff.
From October 6 to October 20
Digging wok in progress on both sides of Taxiway A and B abeam holding point of Runway 03l/21R (02 feet wide and 03 feet deep) and approximately 65 feet from both taxiways centre line. All pilots advised to exercise caution while landing/takeoff.
Digging work in progress on both sides of Taxiway A and B abeam holding points of Runway 03L/21R (02 feet wide and 03 feet deep) and approximately 65 feet from both taxiways centre line. All pilots advised to exercise caution while taxiing.
From October 18 to December 31
Digging wok in progress on western side from threshold Runway 03L up to abeam Taxiway A and from abeam Taxiway B to 3500 feet down Runway 03L (02 feet wide and 03 feet deep). Digging is 75 feet from runway centre line. All pilots advised to exercise caution while landing/takeoff.