New Link Taxiway and Runway Turn Pad to be Constructed for Sialkot Airport Runway
-
- Site Admin
- Posts: 52155
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Rapid Exit Taxiway to be Constructed for Sialkot Airport Runway
From August 22 to September 15
Dumbbell shoulder cutting work for fixing of edge lights at newly constructed dumbbell of Runway 22 in progress. Labor and usable material may be present 25 meters to 50 meters from shoulder edge. There will be no work during landing/takeoff.
Abbas
Dumbbell shoulder cutting work for fixing of edge lights at newly constructed dumbbell of Runway 22 in progress. Labor and usable material may be present 25 meters to 50 meters from shoulder edge. There will be no work during landing/takeoff.
Abbas
-
- Site Admin
- Posts: 52155
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Rapid Exit Taxiway to be Constructed for Sialkot Airport Runway
From September 10 to October 14
Dumbbell shoulder cutting work for fixing of edge lights at newly constructed dumbbell of Runway 22 in progress. Labor and usable material may be present 25 meters to 50 meters from shoulder edge. There will be no work during landing/takeoff.
Abbas
Dumbbell shoulder cutting work for fixing of edge lights at newly constructed dumbbell of Runway 22 in progress. Labor and usable material may be present 25 meters to 50 meters from shoulder edge. There will be no work during landing/takeoff.
Abbas
-
- Registered Member
- Posts: 4672
- Joined: Sun May 01, 2005 12:09 pm
- Location: Kuwait
Re: Rapid Exit Taxiway to be Constructed for Sialkot Airport Runway
2 changes notable at following map links
additional taxiway connecting runway 04/22 with the ramp https://satellites.pro/Pakistan_map#32. ... .367335,16
additional dumbbell constructed of runway 22 https://satellites.pro/Pakistan_map#32. ... .376411,17
additional taxiway connecting runway 04/22 with the ramp https://satellites.pro/Pakistan_map#32. ... .367335,16
additional dumbbell constructed of runway 22 https://satellites.pro/Pakistan_map#32. ... .376411,17
Raihan SR Bakhsh
flickr.com/photos/raihanshahzad
EY-B77W, A345, A320, A319, EK-B773, B77W, A388, FZ-B738, GF-L1011, B732, A332, A320, A319, KU-A343, AB6, A310, A320, NL-A320, PK-B707/720, B733, B772, B77L, AB4, A310, A320, QR-A320, A321, A333, A359, A35X, B77W, B788, WY-B738, B739, A333
flickr.com/photos/raihanshahzad
EY-B77W, A345, A320, A319, EK-B773, B77W, A388, FZ-B738, GF-L1011, B732, A332, A320, A319, KU-A343, AB6, A310, A320, NL-A320, PK-B707/720, B733, B772, B77L, AB4, A310, A320, QR-A320, A321, A333, A359, A35X, B77W, B788, WY-B738, B739, A333
-
- Site Admin
- Posts: 52155
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Rapid Exit Taxiway to be Constructed for Sialkot Airport Runway
From September 23 to November 30.
All aircraft while making 180 degree turn at the end of Runway 04/22 shall use dumb bell/turn pad for backtracking or lining up and follow yellow center line.
Digging work in progress for construction of new link taxiway, east of existing taxiway from apron edge to lateral limits of runway shoulder. Runway shoulder not available between 2000 meters to 2150 meters north-east down Runway 04. Machinery and manpower deployed. Day/night marking provided. Pilots advised to exercise caution while landing/takeoff. Strictly follow center line of runway while taxing. Follow-me may be provided on request.
Abbas
All aircraft while making 180 degree turn at the end of Runway 04/22 shall use dumb bell/turn pad for backtracking or lining up and follow yellow center line.
Digging work in progress for construction of new link taxiway, east of existing taxiway from apron edge to lateral limits of runway shoulder. Runway shoulder not available between 2000 meters to 2150 meters north-east down Runway 04. Machinery and manpower deployed. Day/night marking provided. Pilots advised to exercise caution while landing/takeoff. Strictly follow center line of runway while taxing. Follow-me may be provided on request.
Abbas
-
- Site Admin
- Posts: 52155
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Rapid Exit Taxiway to be Constructed for Sialkot Airport Runway
From October 6 to November 30
Dumbbell shoulder cutting work for fixing of edge lights at newly constructed dumbbell of Runway 22 in progress. Labor and usable material may be present 25 meters to 50 meters from shoulder edge. There will be no work during landing/takeoff.
Abbas
Dumbbell shoulder cutting work for fixing of edge lights at newly constructed dumbbell of Runway 22 in progress. Labor and usable material may be present 25 meters to 50 meters from shoulder edge. There will be no work during landing/takeoff.
Abbas
-
- Site Admin
- Posts: 52155
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Rapid Exit Taxiway to be Constructed for Sialkot Airport Runway
From November 13 to December 31, between dawn to dusk excavation work for one meter deep ditch is in progress on right side on Runway 04 from 1300 meters down the runway up to 1750 meters from dawn to dusk.
Machinery and manpower is deployed 20 meters from runway shoulder edge towards right side of Runway 04. There will be no work during landing and takeoff. Pilots advised to exercise caution.
Abbas
Machinery and manpower is deployed 20 meters from runway shoulder edge towards right side of Runway 04. There will be no work during landing and takeoff. Pilots advised to exercise caution.
Abbas
-
- Site Admin
- Posts: 52155
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Rapid Exit Taxiway to be Constructed for Sialkot Airport Runway
From November 21, 2020, to May 31, 2021
All aircraft while making 180 degree turn at the end of Runway 04/22 shall use dumbbell for back tracking or lining up and follow yellow center line.
From November 21, 2020, to February 28, 2021
Dumbbell shoulder cutting work for fixing of edge lights at newly constructed dumbbell of Runway 22 in progress. Labor and usable material may be present 25 meters to 50 meters from shoulder edge. There will be no work during landing/takeoff.
Abbas
All aircraft while making 180 degree turn at the end of Runway 04/22 shall use dumbbell for back tracking or lining up and follow yellow center line.
From November 21, 2020, to February 28, 2021
Dumbbell shoulder cutting work for fixing of edge lights at newly constructed dumbbell of Runway 22 in progress. Labor and usable material may be present 25 meters to 50 meters from shoulder edge. There will be no work during landing/takeoff.
Abbas
-
- Site Admin
- Posts: 52155
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Rapid Exit Taxiway to be Constructed for Sialkot Airport Runway
From December 21, 2020, to January 31, 2021, excavation work for one meter deep ditch is in progress on right side on Runway 04 from 1300 meters down the runway up to 1750 meters from dawn to dusk.
Machinery and manpower is deployed 20 meters from runway shoulder edge towards right side of Runway 04. There will be no work during landing and takeoff. Pilots advised to exercise caution.
Abbas
Machinery and manpower is deployed 20 meters from runway shoulder edge towards right side of Runway 04. There will be no work during landing and takeoff. Pilots advised to exercise caution.
Abbas
-
- Site Admin
- Posts: 52155
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Rapid Exit Taxiway to be Constructed for Sialkot Airport Runway
From January 19, 2021 to April 30, 2021, excavation work for one meter deep ditch is in progress on right side on Runway 04 from 1300 meters down the runway up to 1750 meters from dawn to dusk.
Machinery and manpower is deployed 20 meters from runway shoulder edge towards right side of Runway 04. There will be no work during landing and takeoff. Pilots advised to exercise caution.
Abbas
Machinery and manpower is deployed 20 meters from runway shoulder edge towards right side of Runway 04. There will be no work during landing and takeoff. Pilots advised to exercise caution.
Abbas
-
- Site Admin
- Posts: 52155
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Rapid Exit Taxiway to be Constructed for Sialkot Airport Runway
From February 18 to March 31
Dumbbell shoulder cutting work for fixing of edge lights on newly constructed dumbbell of Runway 22 in progress. Labor and usable material may be present 25 meters to 50 meters from shoulder edge. There will be no work during landing/takeoff.
Abbas
Dumbbell shoulder cutting work for fixing of edge lights on newly constructed dumbbell of Runway 22 in progress. Labor and usable material may be present 25 meters to 50 meters from shoulder edge. There will be no work during landing/takeoff.
Abbas
-
- Site Admin
- Posts: 52155
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Rapid Exit Taxiway to be Constructed for Sialkot Airport Runway
From April 17 to July 31
Work in progress on under construction taxiway from 2150 meters down Runway 04. All pilots advised to exercise caution while taxiing to/from apron.
Abbas
Work in progress on under construction taxiway from 2150 meters down Runway 04. All pilots advised to exercise caution while taxiing to/from apron.
Abbas
-
- Site Admin
- Posts: 52155
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Rapid Exit Taxiway to be Constructed for Sialkot Airport Runway
From May 1, 2021 to May 15, 2021, from dawn to dusk excavation work for one meter deep ditch is in progress on right side on Runway 04 from 1300 meters down the runway up to 1750 meters from dawn to dusk.
Machinery and manpower is deployed 20 meters from runway shoulder edge towards right side of Runway 04. There will be no work during landing and takeoff. Pilots advised to exercise caution.
Abbas
Machinery and manpower is deployed 20 meters from runway shoulder edge towards right side of Runway 04. There will be no work during landing and takeoff. Pilots advised to exercise caution.
Abbas
-
- Site Admin
- Posts: 52155
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Rapid Exit Taxiway and Dumbbell to be Constructed for Sialkot Airport Runway
From May 19, 2021, all aircraft making 180 degree turn at the end of Sialkot Airport Runway 04/22 shall use dumbbell for back tracking or lining-up and follow yellow center line.
Abbas
Abbas
-
- Site Admin
- Posts: 52155
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Rapid Exit Taxiway and Dumbbell to be Constructed for Sialkot Airport Runway
From July 19 to August 31
Work in progress under construction taxiway from 2150 meters down Runway 04. All pilots to exercise caution while taxiing to/from apron.
Abbas
Work in progress under construction taxiway from 2150 meters down Runway 04. All pilots to exercise caution while taxiing to/from apron.
Abbas
-
- Site Admin
- Posts: 52155
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Rapid Exit Taxiway and Dumbbell to be Constructed for Sialkot Airport Runway
From August 23 to October 31
Work in progress under construction taxiway. From 2150 meter down Runway 04. All pilots to exercise caution while taxiing to/from Apron.
Abbas
Work in progress under construction taxiway. From 2150 meter down Runway 04. All pilots to exercise caution while taxiing to/from Apron.
Abbas