New Link Taxiway and Runway Turn Pad to be Constructed for Sialkot Airport Runway

Discuss issues and news related to PIA, Pakistani airlines and Pakistan's civil & military aviation.
User avatar
Abbas Ali
Site Admin
Posts: 52155
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Rapid Exit Taxiway to be Constructed for Sialkot Airport Runway

Post by Abbas Ali »

From August 22 to September 15

Dumbbell shoulder cutting work for fixing of edge lights at newly constructed dumbbell of Runway 22 in progress. Labor and usable material may be present 25 meters to 50 meters from shoulder edge. There will be no work during landing/takeoff.

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 52155
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Rapid Exit Taxiway to be Constructed for Sialkot Airport Runway

Post by Abbas Ali »

From September 10 to October 14

Dumbbell shoulder cutting work for fixing of edge lights at newly constructed dumbbell of Runway 22 in progress. Labor and usable material may be present 25 meters to 50 meters from shoulder edge. There will be no work during landing/takeoff.

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
raihans
Registered Member
Posts: 4672
Joined: Sun May 01, 2005 12:09 pm
Location: Kuwait

Re: Rapid Exit Taxiway to be Constructed for Sialkot Airport Runway

Post by raihans »

2 changes notable at following map links

additional taxiway connecting runway 04/22 with the ramp https://satellites.pro/Pakistan_map#32. ... .367335,16

additional dumbbell constructed of runway 22 https://satellites.pro/Pakistan_map#32. ... .376411,17
Raihan SR Bakhsh

flickr.com/photos/raihanshahzad
EY-B77W, A345, A320, A319, EK-B773, B77W, A388, FZ-B738, GF-L1011, B732, A332, A320, A319, KU-A343, AB6, A310, A320, NL-A320, PK-B707/720, B733, B772, B77L, AB4, A310, A320, QR-A320, A321, A333, A359, A35X, B77W, B788, WY-B738, B739, A333
User avatar
Abbas Ali
Site Admin
Posts: 52155
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Rapid Exit Taxiway to be Constructed for Sialkot Airport Runway

Post by Abbas Ali »

From September 23 to November 30.

All aircraft while making 180 degree turn at the end of Runway 04/22 shall use dumb bell/turn pad for backtracking or lining up and follow yellow center line.

Digging work in progress for construction of new link taxiway, east of existing taxiway from apron edge to lateral limits of runway shoulder. Runway shoulder not available between 2000 meters to 2150 meters north-east down Runway 04. Machinery and manpower deployed. Day/night marking provided. Pilots advised to exercise caution while landing/takeoff. Strictly follow center line of runway while taxing. Follow-me may be provided on request.

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 52155
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Rapid Exit Taxiway to be Constructed for Sialkot Airport Runway

Post by Abbas Ali »

From October 6 to November 30

Dumbbell shoulder cutting work for fixing of edge lights at newly constructed dumbbell of Runway 22 in progress. Labor and usable material may be present 25 meters to 50 meters from shoulder edge. There will be no work during landing/takeoff.

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 52155
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Rapid Exit Taxiway to be Constructed for Sialkot Airport Runway

Post by Abbas Ali »

From November 13 to December 31, between dawn to dusk excavation work for one meter deep ditch is in progress on right side on Runway 04 from 1300 meters down the runway up to 1750 meters from dawn to dusk.

Machinery and manpower is deployed 20 meters from runway shoulder edge towards right side of Runway 04. There will be no work during landing and takeoff. Pilots advised to exercise caution.

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 52155
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Rapid Exit Taxiway to be Constructed for Sialkot Airport Runway

Post by Abbas Ali »

From November 21, 2020, to May 31, 2021

All aircraft while making 180 degree turn at the end of Runway 04/22 shall use dumbbell for back tracking or lining up and follow yellow center line.

Image

From November 21, 2020, to February 28, 2021

Dumbbell shoulder cutting work for fixing of edge lights at newly constructed dumbbell of Runway 22 in progress. Labor and usable material may be present 25 meters to 50 meters from shoulder edge. There will be no work during landing/takeoff.

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 52155
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Rapid Exit Taxiway to be Constructed for Sialkot Airport Runway

Post by Abbas Ali »

From December 21, 2020, to January 31, 2021, excavation work for one meter deep ditch is in progress on right side on Runway 04 from 1300 meters down the runway up to 1750 meters from dawn to dusk.

Machinery and manpower is deployed 20 meters from runway shoulder edge towards right side of Runway 04. There will be no work during landing and takeoff. Pilots advised to exercise caution.

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 52155
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Rapid Exit Taxiway to be Constructed for Sialkot Airport Runway

Post by Abbas Ali »

From January 19, 2021 to April 30, 2021, excavation work for one meter deep ditch is in progress on right side on Runway 04 from 1300 meters down the runway up to 1750 meters from dawn to dusk.

Machinery and manpower is deployed 20 meters from runway shoulder edge towards right side of Runway 04. There will be no work during landing and takeoff. Pilots advised to exercise caution.

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 52155
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Rapid Exit Taxiway to be Constructed for Sialkot Airport Runway

Post by Abbas Ali »

From February 18 to March 31

Dumbbell shoulder cutting work for fixing of edge lights on newly constructed dumbbell of Runway 22 in progress. Labor and usable material may be present 25 meters to 50 meters from shoulder edge. There will be no work during landing/takeoff.

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 52155
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Rapid Exit Taxiway to be Constructed for Sialkot Airport Runway

Post by Abbas Ali »

From April 17 to July 31

Work in progress on under construction taxiway from 2150 meters down Runway 04. All pilots advised to exercise caution while taxiing to/from apron.

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 52155
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Rapid Exit Taxiway to be Constructed for Sialkot Airport Runway

Post by Abbas Ali »

From May 1, 2021 to May 15, 2021, from dawn to dusk excavation work for one meter deep ditch is in progress on right side on Runway 04 from 1300 meters down the runway up to 1750 meters from dawn to dusk.

Machinery and manpower is deployed 20 meters from runway shoulder edge towards right side of Runway 04. There will be no work during landing and takeoff. Pilots advised to exercise caution.

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 52155
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Rapid Exit Taxiway and Dumbbell to be Constructed for Sialkot Airport Runway

Post by Abbas Ali »

From May 19, 2021, all aircraft making 180 degree turn at the end of Sialkot Airport Runway 04/22 shall use dumbbell for back tracking or lining-up and follow yellow center line.

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 52155
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Rapid Exit Taxiway and Dumbbell to be Constructed for Sialkot Airport Runway

Post by Abbas Ali »

From July 19 to August 31

Work in progress under construction taxiway from 2150 meters down Runway 04. All pilots to exercise caution while taxiing to/from apron.

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 52155
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Rapid Exit Taxiway and Dumbbell to be Constructed for Sialkot Airport Runway

Post by Abbas Ali »

From August 23 to October 31

Work in progress under construction taxiway. From 2150 meter down Runway 04. All pilots to exercise caution while taxiing to/from Apron.