New Link Taxiway and Runway Turn Pad to be Constructed for Sialkot Airport Runway
-
- Site Admin
- Posts: 52298
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
New Link Taxiway and Runway Turn Pad to be Constructed for Sialkot Airport Runway
In March 23 newspaper:
Sialkot International Airport Limited (SIAL) invites applications for pre-qualification for the construction of rapid exit taxiway & dumbbell and repair of existing runway at Sialkot International Airport.
Abbas
Sialkot International Airport Limited (SIAL) invites applications for pre-qualification for the construction of rapid exit taxiway & dumbbell and repair of existing runway at Sialkot International Airport.
Abbas
Last edited by Abbas Ali on Sun Jan 30, 2022 3:01 pm, edited 1 time in total.
Reason: Topic title edited.
Reason: Topic title edited.
-
- Site Admin
- Posts: 52298
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Rapid Exit Taxiway to be Constructed for Sialkot Airport Runway
Runway 04/22 of Sialkot International Airport (SIAL).
Abbas
Abbas
-
- Registered Member
- Posts: 4672
- Joined: Sun May 01, 2005 12:09 pm
- Location: Kuwait
Re: Rapid Exit Taxiway to be Constructed for Sialkot Airport Runway
Silakot Airport has 2 dumbbells each on runway end 04/22 though this additional dumbbell might be needed after taxiway 'A' as most traffic approach runway 04 so they can backtrack early rather then going end of runway and backtrack using runway 22 dumbbell which takes lot of time and extra fuel consumption.
btw, rapid exit taxiway will require a proper taxiway parallel to runway whereas Sialkot airport has no plan for taxiway yet so where they want the traffic to vacate runway using rapid exit taxiway?
btw, rapid exit taxiway will require a proper taxiway parallel to runway whereas Sialkot airport has no plan for taxiway yet so where they want the traffic to vacate runway using rapid exit taxiway?
Raihan SR Bakhsh
flickr.com/photos/raihanshahzad
EY-B77W, A345, A320, A319, EK-B773, B77W, A388, FZ-B738, GF-L1011, B732, A332, A320, A319, KU-A343, AB6, A310, A320, NL-A320, PK-B707/720, B733, B772, B77L, AB4, A310, A320, QR-A320, A321, A333, A359, A35X, B77W, B788, WY-B738, B739, A333
flickr.com/photos/raihanshahzad
EY-B77W, A345, A320, A319, EK-B773, B77W, A388, FZ-B738, GF-L1011, B732, A332, A320, A319, KU-A343, AB6, A310, A320, NL-A320, PK-B707/720, B733, B772, B77L, AB4, A310, A320, QR-A320, A321, A333, A359, A35X, B77W, B788, WY-B738, B739, A333
-
- Site Admin
- Posts: 52298
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Rapid Exit Taxiway to be Constructed for Sialkot Airport Runway
I think before the end of runway on one side a dumbbell will be constructed to allow the aircraft to turnaround & backtrack before the end of the runway.
And, before the end of runway on other side a rapid exit taxiway will be built to allow the aircraft to leave the runway before the end of the runway.
So, a dumbbell before the end of runway on one side and a rapid exit taxiway before the end of runway on the other side.
Abbas
And, before the end of runway on other side a rapid exit taxiway will be built to allow the aircraft to leave the runway before the end of the runway.
So, a dumbbell before the end of runway on one side and a rapid exit taxiway before the end of runway on the other side.
Abbas
-
- Registered Member
- Posts: 7
- Joined: Tue Jul 12, 2016 11:58 am
Re: Rapid Exit Taxiway to be Constructed for Sialkot Airport Runway
Last month, while waiting in the lounge, i saw Air Arabia A320 landing Runway 04 able to exit via Taxiway with no backtracking although it is short distance.
-
- Site Admin
- Posts: 52298
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Sialkot Airport Link Taxiway Number Two to be Constructed
Sialkot International Airport Limited (SIAL) bids invitation in August 5 newspaper for construction of link taxiway number two, dumbbell at Runway 22 end and repair of existing runway.
Abbas
Abbas
-
- Site Admin
- Posts: 52298
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Sialkot Airport Link Taxiway Number Two to be Constructed
Sialkot International Airport Runway 04/22.
Abbas
Abbas
-
- Site Admin
- Posts: 52298
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Sialkot Airport Link Taxiway Number Two to be Constructed
Sialkot Internatioinal Airport Limited (SIAL) tender notice in September 9 newspaper for airfield lighting & associated works (Phase-I) for Link Taxiway and Dumbell at End 22 at Sialkot International Airport.
Abbas
Abbas
-
- Site Admin
- Posts: 52298
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Sialkot Airport Link Taxiway Number Two to be Constructed
Digging work has begun for the construction of new link taxiway. Machinery and manpower deployed. Pilots advised to exercise caution while landing and takeoff and strictly follow center line of runway while taxiing.
Work duration from October 16, 2019 to January 31, 2020.
NOTAM issued by Pakistan CAA.
Abbas
Work duration from October 16, 2019 to January 31, 2020.
NOTAM issued by Pakistan CAA.
Abbas
-
- Site Admin
- Posts: 52298
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Sialkot Airport Link Taxiway Number Two to be Constructed
Digging work in progress for construction of new link taxiway, east of existing taxiway from apron edge to lateral limits of runway shoulder. Runway shoulder not available between 200 meters to 2150 meters north-east down Runway 04. Machinery and manpower deployed. Day/night markings provided. Pilots to exercise caution while landing/takeoff. Strictly follow center line of runway while taxiing. 'Follow Me' vehicle may be provided on request.
Work duration from January 15 to April 30.
NOTAM issued by Pakistan CAA.
Abbas
Work duration from January 15 to April 30.
NOTAM issued by Pakistan CAA.
Abbas
-
- Site Admin
- Posts: 52298
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Rapid Exit Taxiway to be Constructed for Sialkot Airport Runway
From March 25 to June 4 all aircraft approaching Runway 22 threshold and after landing on Runway 04 or lining up for Runway 22 for depature shall use Runway 22 pocket for anti-clock wise turn from 9000 feet down Runway 04. Left-side shoulder not available due to construction of new pocket North-East of the runway. Heavy machinery and manpower deployed. Pilots advised to exercise caution while landing/takeoff.
Sialkot Airport Runway 22 threshold.
Abbas
Sialkot Airport Runway 22 threshold.
Abbas
-
- Site Admin
- Posts: 52298
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Sialkot Airport Link Taxiway Number Two to be Constructed
From April 17 to July 31, digging work for the construction of new link taxiway, east of existing taxiway from apron edge to lateral limits of runway shoulder. Runway shoulder not available between 200 meters to 2150 meters north-east down Runway 04. Machinery and manpower deployed. Day/night markings provided. Pilots to exercise caution while landing/takeoff. Strictly follow center line of runway while taxiing. 'Follow Me' vehicle may be provided on request.
Abbas
Abbas
-
- Site Admin
- Posts: 52298
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Sialkot Airport Link Taxiway Number Two to be Constructed
From July 20 to September 30, digging work for the construction of new link taxiway, east of existing taxiway from apron edge to lateral limits of runway shoulder. Runway shoulder not available between 2000 meters to 2150 meters north-east down Runway 04. Machinery and manpower deployed. Day/night markings provided. Pilots to exercise caution while landing/takeoff. Strictly follow center line of runway while taxiing. 'Follow Me' vehicle may be provided on request.
Abbas
Abbas
-
- Site Admin
- Posts: 52298
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Rapid Exit Taxiway to be Constructed for Sialkot Airport Runway
From July 28 to August 15
Dumbbell shoulder cutting work for fixing of edge lights at newly constructed dumbbell of Runway 22 in progress. Labour and useable material may be present 25 meters to 50 meters from shoulder edge. There will be now work during aircraft landing/takeoff.
Abbas
Dumbbell shoulder cutting work for fixing of edge lights at newly constructed dumbbell of Runway 22 in progress. Labour and useable material may be present 25 meters to 50 meters from shoulder edge. There will be now work during aircraft landing/takeoff.
Abbas
-
- Site Admin
- Posts: 52298
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Rapid Exit Taxiway to be Constructed for Sialkot Airport Runway
From August 13 to August 25
Dumbbell shoulder cutting work for fixing of edge lights at newly constructed dumbbell of Runway 22 in progress. Labor and usable material may be present 25 meters to 50 meters from shoulder edge. There will be no work during landing/takeoff.
From August 13 to November 30
All aircraft while making 180 degree turn at the end of Runway 04/22 shall use dumb bell for backtracking or lining up and follow yellow center line.
Abbas
Dumbbell shoulder cutting work for fixing of edge lights at newly constructed dumbbell of Runway 22 in progress. Labor and usable material may be present 25 meters to 50 meters from shoulder edge. There will be no work during landing/takeoff.
From August 13 to November 30
All aircraft while making 180 degree turn at the end of Runway 04/22 shall use dumb bell for backtracking or lining up and follow yellow center line.
Abbas