In today's (November 22) newspaper.
Pakistan Civil Aviation Authority (CAA)
Pre-qualification Notice
For Construction & Operation of Cargo Village at Jinnah International Air Port (JIAP) - Karachi
Jinnah International Airport, Karachi, is the largest and busiest airport of Pakistan. With current cargo movement of 160,124 metric ton/year coupled with decent growth need for world class cargo village is inevitable. Existing condition of cargo terminal and plan for new cargo village create opportunity for renowned and reputable companies to Build-Operate-Transfer (BOT) under Public-Private Partnership (PPP) modality.
Cargo Village shall provide facilities and infrastructure including bounded areas and customs offices, warehouses, domestic cargo terminal, light industrial area, cold storages, services for airlines and freight forwarders, business centre, food court, canteen, banks, automated teller machine (ATM), prayer area, conference rooms and ample parking area.
Abbas
Cargo Village to be Constructed at Karachi Airport
-
- Site Admin
- Posts: 52293
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
-
- Site Admin
- Posts: 52293
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Cargo Village to be Constructed at Karachi Airport
According to following corrigendum in today's (December 13) newspaper, date of submission for pre-qualification documents for construction & operation of cargo village at Jinnah International Air Port (JIAP) - Karachi has been extended to December 26, 2014.
Abbas
Abbas
-
- Site Admin
- Posts: 52293
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Cargo Village to be Constructed at Karachi Airport
In today's (October 23) newspaper:
Request for Expression of Interest
Pre-qualification of bidders to design, build, operate & transfer Cargo Village project at Jinnah International Air Port (JIAP) - Karachi
Jinnah International Air Port (JIAP) - Karachi is Pakistan's largest international & domestic airport with respect to commercial aircraft movements, passengers and cargo.
JIAP - Karachi contributes to around 50% of the total air cargo from Pakistan. Cargo movement during CY2014 was 160,124 metric tons. CAA plans to revamp the cargo facilities and operations at JIAP by building a new Cargo Village. The complex is expected to provide additional space and improved infrastructure and facilities, which may be expanded on the basis of an approved master plan.
The project is envisaged to be developed on a Build-Operate-Transfer (BOT) modality by award of a 30 year concession to a private developer and operator. The concessionaire shall be responsible to design, build and operate the facility, which shall be transferred to Civil Aviation Authority (CAA) upon expiry of the concession period.
Abbas
Request for Expression of Interest
Pre-qualification of bidders to design, build, operate & transfer Cargo Village project at Jinnah International Air Port (JIAP) - Karachi
Jinnah International Air Port (JIAP) - Karachi is Pakistan's largest international & domestic airport with respect to commercial aircraft movements, passengers and cargo.
JIAP - Karachi contributes to around 50% of the total air cargo from Pakistan. Cargo movement during CY2014 was 160,124 metric tons. CAA plans to revamp the cargo facilities and operations at JIAP by building a new Cargo Village. The complex is expected to provide additional space and improved infrastructure and facilities, which may be expanded on the basis of an approved master plan.
The project is envisaged to be developed on a Build-Operate-Transfer (BOT) modality by award of a 30 year concession to a private developer and operator. The concessionaire shall be responsible to design, build and operate the facility, which shall be transferred to Civil Aviation Authority (CAA) upon expiry of the concession period.
Abbas
-
- Site Admin
- Posts: 52293
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Cargo Village to be Constructed at Karachi Airport
Date extended to December 28, 2015, for submission of Expression of Interest (EoI) for Cargo Village Project at Karachi Airport, according to following corrigendum in today's (November 27) newspaper.
Abbas
Abbas
-
- Site Admin
- Posts: 52293
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Cargo Village to be Constructed at Karachi Airport
Date extended to February 2, 2016, for submission of Expression of Interest (EoI) for Cargo Village Project at Karachi Airport, according to following corrigendum in today's (December 29) newspaper.
Abbas
Abbas
-
- Registered Member
- Posts: 1
- Joined: Fri Feb 05, 2016 10:26 am
Re: Cargo Village to be Constructed at Karachi Airport
any news about cargo village?